The Met Office has issued a yellow warning for ice from 6pm Monday 16 February to 10am Tuesday 17 February.
If you see a highways emergency, please call 0345 606 6171.
Find out more about severe weather affecting Suffolk, including how to prepare.
The Met Office has issued a yellow warning for ice from 6pm Monday 16 February to 10am Tuesday 17 February.
If you see a highways emergency, please call 0345 606 6171.
Find out more about severe weather affecting Suffolk, including how to prepare.

The works are programmed to commence on Monday 29 September 2025 and, at present, we are aiming to complete them by early summer 2026.
The project will involve reconfiguring the junction, replacing the current one-way clockwise system to enable two-way traffic in all directions.
Phase Three
When will we be working?
Works along the east of Fornham Road commenced earlier this month. We plan to complete these works in April.
What will we be doing?
We will be upgrading and reconstructing each phase of the outer gyratory, including new, wider shared use footways, drainage, signals and streetlighting. This will also include new Dutch Style crossings to the Tollgate Public House, Bell Meadow, and service road to the south.
Works have commenced along Fornham Road east and will continue towards the extent of our scheme opposite Sandy Lane. Concurrently, teams will also begin works within the existing junction of Tollgate Lane and Fornham Road, upgrading the footways and signalised crossings in this area.
Additionally, third party utility contractors will be completing UKPN connection works along Fornham Road at the Junction with Tollgate Lane. These works are not associated with the scheme but are being undertaken in collaboration with Suffolk Highways to reduce the requirement for future road closures, helping to minimise disruption to the local community.
What traffic management will be in place?
For the safety of highway users, especially vehicles travelling along Fornham Road, and our operatives, Norfolk Road at the Junction with Fornham Road will be closed at all times from 26 January until early April. Access to and from Norfolk Road will be maintained via the signed diversion: Norfolk Road – Northgate Avenue – Avenue Approach – Fornham Road and vice versa . Narrow lanes will also be installed along Fornham Road.
In addition, the inbound closure of Thetford Road and left turn only from Bell Meadow will remain in place through this phase of works.
To enable works on the new signal system, the existing permanent signals, which have been utilised since the start of construction, will be replaced with temporary signals and crossing points on Tollgate Lane and Mildenhall Road whilst a single lane closure is established at each of the key works locations. These will be installed during the week commencing 19 January.
During this time, there may also be a requirement to close and divert footways. A signed route will always be maintained around the gyratory, either clockwise or anti clockwise, so please follow footway and pedestrian signage accordingly.
Following the completion of phase three, we will commence phase four of the works. Please see below for further details on this.
Phase Four
When will we be working?
We will commence this phase once phase three is completed, which we anticipate will be in mid to late April time. Works on site will then conclude in May, if not sooner.
What will we be doing?
Works will include full resurfacing of the junction, lining, signage installation, and the installation and commissioning of new traffic signals. Following this, traffic will be switched to permanent headings, removing the existing gyratory system. Further details of the permanent changes to the gyratory system will be communicated ahead of these planned changes.
What traffic management will be in place for these works?
For the safety of highway users and our operatives, a full closure of the Tollgate Gyratory, except for access, will be in operation whilst we carry out our works overnight. We anticipate that this closure will be in place between 7pm to 6am during weekdays only for a period of approximately three weeks.
The inbound closure of Thetford Road and left turn only from Bell Meadow will also remain in place.
We will continue to provide updates regarding progress on the scheme and will notify you of any changes brought about by future phases before they commence.
What will we be doing?
Footway improvement works.
Where will we be doing it?
Greenfields Way, Haverhill.
What are the times and dates of the works?
From Monday 20 November 2025 until Friday 6 February 2026. There will be a break over the festive period, during which traffic management will be removed from site.
What traffic management will be in place?
While we are working, temporary traffic lights will be in place around the works area for the safety of highway users and our operatives. Footway closures will also be in place.
What will I need to do in advance?
To ensure these works commence and progress smoothly, please do not park your vehicle on the road shortly before they are scheduled to begin, as will as throughout their duration.
'No Parking' cones will be placed on the road in advance to indicate where we will be working.
We will be working on one short section of footway at a time. While the works are underway, temporary traffic lights will be placed around the area. The section of footway we are working on will also be closed, for the safety of pedestrians.
What will we be doing?
Footway improvement works
Where will we be doing it?
Beech Grove and Western Avenue, Haverhill
What are the times and dates of the works?
Between 9am and 3pm from Monday 5 January until Monday 16 February 2026.
What traffic management will be in place?
While we are working, a road closure will be in place for the safety of highway users and our operatives.
What is the diversion route?
Eastern Avenue, A1307, Western Avenue and vice versa.
To reduce the impact, these works will be carried out in phases. A road closure will only be installed once the first phase has been completed.
To ensure that these works commence and progress smoothly, we are asking residents not to park their vehicles on the road shortly before they are scheduled to begin, as well as through their duration.
'No Parking' cones will be placed on the road in advance to indicate where we will be working.
What will we be doing?
Footway improvement works.
Where will we be doing it?
Northumberland Avenue, Bury St Edmunds.
What are the dates of the works?
From Monday 26 January 2026 to Friday 24 April 2026.
What traffic management will be in place?
While we are working, a road closure will be in place for the safety of highway users and our operatives.
What is the diversion route?
Northumberland Road, Baldwin Avenue, Lancaster Avenue and vice versa.
Additional info:
These works from phase two of our footway improvements along Northumberland Avenue, following the completion of phase one in 2024. Once phase two is complete, we will move on to phase three of the works and provide a further update closer to its commencement.
To ensure these works commence and progress smoothly, please do not park your vehicles on the road shortly before they are scheduled to begin as well as throughout their duration.
'No Parking' cones will be placed on the road in advance to indicate where we will be working.
What will we be doing?
Footway improvements.
Where will we be doing it?
Melford Road, Lavenham - between the junction with Peek Close and the junction with Green Willows.
What are the dates of the works?
From Monday 2 February until Friday 20 February.
What traffic management will be in place?
While we are working, a road closure will be in place for the safety of highway users and our operatives.
What is the diversion route?
B1071, B1115, Waldingfield Road, High Street, Melford Road, Bull Lane, Lavenham Road, Melford Road and vice versa.
What will we be doing?
Drainage investigations.
Where will we be doing it?
Main Road, Somersham.
What are the times and dates of the works?
Between 10am and 2:30pm from Monday 9 February until Friday 13 February.
What traffic management will be in place?
While we are working, a road closure will be in place for the safety of highway users and our operatives.
To reduce the impact of these works, they will be carried out in two phases.
Phase 1: Between Hall Lane and Church Lane.
Phase 2: Between Church Lane and Somersham Road.
Phase 2 will begin following the completion of Phase 1.
What is the diversion route?
For Both Phases: Somersham Road, Leather Bottle Hill, Somersham Road, B1113, Grinstead Hill, B1078, Willisham Road, Main Road, Willisham Hall Road, Ipswich Road, Main Road and vice versa.
What will we be doing?
Carriageway resurfacing.
Where will we be doing it?
A143 Bury Road, Great Barton.
What are the times and dates of the works?
Between 8pm and 5am from Monday 16 February until Friday 27 February, excluding weekends.
What traffic management will be in place?
While we are working, a road closure will be in place for the safety of highways users and our operatives.
What is the diversion route?
A143, A14, A140, A143 and vice versa.
What will we be doing?
Essential drainage improvement and reconstruction works to address flooding concerns.
Where will we be doing it?
Barking Road, Needham - from Parsons Lane to Foxglove Avenue.
Needham Road Barking.
What are the dates of the works?
From Monday 23 February until Friday 24 April.
Please note, the closure will be lifted between 12pm Friday 10 April and Monday 13 April to accommodate the annual gala at the Barrandov Opera.
What traffic management will be in place?
While we are working, a road closure will be in place for the safety of highway users and our operatives.
What is the diversion route?
B1078, B1113, A1308, B1115, B1078 and vice versa.
To facilitate this diversion route for all vehicle types, there will be a temporary suspension of the vehicle weight limit along B1113, Badley and Needham Market. The limit will be reinstated once the closure has been lifted.
What will we be doing?
Essential carriageway resurfacing works.
Where will we be doing it?
A137 Wherstead Road, Hawes Street roundabout to A137 from the Strand to Ipswich Road.
What are the times and dates of the works?
8pm-6am from Wednesday 4 March to Saturday 14 March 2026.
What traffic management will be in place?
While we are working, a road closure will be in place for the safety of highway users and our operatives.
To ensure that these works commence and progress smoothly, please do not park your vehicle on the road shortly before they are scheduled to begin, as well as throughout their duration.
'No parking' cones will be placed on the road in advance to indicate where we will be working.
What is the diversion route?
A137, A14, A1189, A1156, A137 and vice versa.