Battery Energy Storage System (BESS) Guidance
Suffolk County Council organised a joint Suffolk-wide procurement for the purpose of obtaining expertise in Battery Energy Storage Systems. Each of the Suffolk’s District and Borough Councils were therefore invited to join this, with Suffolk County Council leading the procurement exercise.
The purpose of the guidance is to provide local authorities across Suffolk with a summary of the current technical background information to solely inform local authority officers, and local members, decision making in relation to Battery Energy Storage Systems, not to replace that decision making.
This guidance would apply where the Council(s) are the determining authority for stand-alone battery projects consented through Town and Country Planning Act 1990 regime and where the Council(s) are the discharging authority for Nationally Significant Infrastructure Projects (and include battery storage as associated development) that have been consented by the Secretary of State under the Planning Act 2008 regime.
The majority of decisions relating to Battery Energy Storage Systems are made by District and Borough Councils, because the vast majority of Battery Storage Projects are consented under the Town and Country Planning Act 1990.
The County Council, as the procuring body for this guidance, recognises potential risks regarding conflict of interest, and the set out processes using its procurement processes to eliminate and minimise potential risks associated with this issue. Finally, it recognised that battery technology continues to evolve rapidly, and the risks and opportunities associated with battery energy storage safety management continue to evolve, therefore the Council will, with its partners, continue to review and update as necessary its guidance and procedures in this matter.