The new primary school will serve families moving into the Ipswich Garden Suburb development and will be run by Paradigm Trust.
The site was due to be made available to Suffolk County Council by developer Crest Nicholson. This handover was due to happen once the required development trigger of 180 occupied homes was reached in September 2025.
However, the transfer was not completed by Crest Nicholson until 5 November 2026.
Although the council has now formally received the site, the delay means there is no longer enough time to construct the school and open safely for pupils in September 2027.
The council and its partners have explored a range of alternatives to try to maintain the original opening date, including temporary accommodation and the possibility of opening part of the school ahead of the main building. However, it has been decided that none of these options can now be delivered safely and practically within the time available.
The council is therefore planning for Henley Gate Primary School to open in September 2028.
Families considering applying for a reception place at the primary school for September 2027 are being advised of the change so they can consider alternative schools before making their preferences.
Current pupil place planning indicates that nearby schools have sufficient capacity to accommodate children from the development in the meantime.
Cllr Tony Gould, Cabinet Member for Education and SEND, at Suffolk County Council, said:
“We know families moving to Henley Gate will be disappointed by this delay, and we share that frustration. We have worked hard with our partners to explore every realistic option for keeping the school on track for September 2027.
“Unfortunately, the school site was transferred to the council significantly later than required and, despite our efforts to find an alternative solution, we simply no longer have sufficient time to safely deliver the school for next September.
“Our priority now is to continue working closely with Paradigm Trust and the Department for Education to progress the project and explore the earliest possible opening date for the school. While the programme is still being finalised, the school could potentially open for September 2028, subject to the necessary approvals and delivery programme.”
Crest Nicholson was required under the Section 106 Agreement to make the school site available once specified development triggers had been reached.
The council’s legal services team has been actively involved in seeking to secure the site.