The application for the Development Consent Order - essentially planning permission - was submitted to the Planning Inspectorate (PINS) by National Grid on Friday 29 August.
PINS has 28 days to determine whether or not to accept the application. Should it be accepted, full details of the project will then be published, with the six-month Examination period likely to begin in early 2026. If consent was then granted, construction could begin in 2027.
Councillor Richard Rout, Suffolk County Council’s Cabinet Member for Devolution, Local Government Reorganisation and NSIPs, said:
“In its current guise, the Norwich to Tilbury pylon project is not suitable. The less damaging alternatives, such as offshore transmission or high voltage direct current undergrounding, have never been fully considered.
“Such a significant and impactful project should not be determined simply for being the cheapest and fastest solution. The Hiorns Report concluded that proposals were premature and would not be needed until the mid-2030s.
“When the full details of National Grid’s application are published next month, we hope they reflect many of the concerns raised by us, and local communities, from consultations and discussions. We have highlighted the need for numerous local mitigations, issues around airfields, construction traffic, public rights of way, removal of existing pylon lines, the list goes on.
“For example, we consider there to be a robust case for undergrounding where the line crosses the Waveney Valley – only to be told earlier this year, that this was not going to happen, and that was that without any alternative mitigation proposed.”
Suffolk County Council’s response to previous consultations for the Norwich to Tilbury project can be found at suffolk.gov.uk