Transport works in Lowestoft

 

Bascule Bridge

The agreed Bascule Bridge closure dates are:

  • 8pm Saturday 2 February to 6am Tuesday 5 February 
  • 8pm Saturday 23 February to 6am Thursday 28 February 
  • 8pm Saturday 15 March to 6am Monday 17 March

In addition to the main closures a further set of overnight closures have been programmed in those are;

Proposed overnight closures (8pm to 6 am) on 5, 6, 12 & 13 February.

It was agreed that the temporary footbridge will remain in place until works are complete and the park and ride at Pakefield will continue during closure days.

Suffolk County Council Works

Gordon Road Refurbishment of Bus station from 7 January 2008 for 3 months. Gordon Road will be closed.

Stradbroke Road / Bloodmoor Road. Essex & Suffolk Water will be undertaking new water main supply to new Fire Station. The works will be mostly off highway and a temporary pedestrian footway will be created. Works are from 2 January 2008 until 28 March 2008.

Cotmer Road / Bridge Road at Dutchmans. Anglian Water will use the opportunity to reline sewers 3 March 2008 for 7 nights. Traffic will be controlled using temporary traffic lights.

Network Rail Works

Prospect Road / Borrow Road rail bridge. Re pointing and repairs of the brickwork. 2 February until 1 March 2008. Network Rail will use the opportunity presented by the main Bascule Bridge scheme closures to repair this bridge.